Dear Sir,
Pls clarify the Iraq project:
1, in the documents, it mentioned there is power project site layout plan drawing, but we did not find, please provide.
3. in the hfo report, the sulpur contain is about 4.4%. and MAN hfo can use hfo with sulpur content max. 5%. If higher than 3%, then to world bank standard, it needs desulphur equipments to be added, and desulpur equipments are expensive, pls inform how to handle.
4. to the documents the 2X8MWhfo power plant is used for black start up, if there is problem of supply power from national grid, then the min. start time for hfo power plant is about 1 minute, so please inform if there is min. start up time requirement for the hfo power project. if with very short start up time, high speed diesel generator sets can be around 10 second, then if agreed to us diesel generator sets we can also supply MTU, Cummins, Perkins, Deutz diesel generator sets with diesel oil as fuel.
5. please inform us if this is a public tender, what kind of role or scope of supply from you wished? |