I have another partner which is the actually producer for the item 1,2, 3 as non GE OEM.
Yangchunlin
Dear Mr. yang chun lin,
Good day! Hope you and yours are doing well.
We are a gas turbine hot section parts manufacturer, which has been in action since 2002 (established in 2000). We are one of the very rare companies in the world having the whole value chain (investment casting, machining and coating) in our control (under one roof) and have so far delivered 100,500 blades and vanes to the power generation market showing very high levels of reliability as a Non-OEM manufacturer, to the customers.
While we started our manufacturing activities under Siemens license (for V94.2 blades and vanes), we developed the knowledge we got from this technology transfer to do reverse engineering on other gas turbines (including GE and ALSTOM machines) and we were successfully providing power plants and other industries with our high quality products.
For GE-F9 (PG9171)E, we can supply all stage buckets and nozzles with following part numbers (for your information we have delivered 170 sets of these products out of our production lines to the power generation industries):
item |
description |
1 |
First Stage Bucket , Drawing No: 314B7168G013 , Including Locking and Sealing Hardware ready to be installed into the machine. |
2 |
Second Stage Bucket , Drawing No: 314B7169G005 , Including Locking and Sealing Hardware ready to be installed into the machine. |
3 |
Third Stage Bucket , Drawing No: 314B7170G005 , Including Locking and Sealing Hardware ready to be installed into the machine. |
4 |
First Stage Nozzle , Drawing No: 109E3736G007, Including Locking and Sealing Hardware and Retaining Ring. |
5 |
Second Stage Nozzle , Drawing No: 119E2064G005, Including Locking and Sealing Hardware ready to be installed into the machine. |
6 |
Third Stage Nozzle , Drawing No: 112E6651G001, Including Locking and Sealing Hardware ready to be installed into the machine. |
Our delivery time for the above items is 8-10 month from P.O and receiving advance payment in our account. We are ready to sell the items subject of your inquiry with the following terms and conditions:
item |
description |
Unit price (Set) in EU Dollar |
1 |
First Stage Bucket , Drawing No: 314B7168G013 , Including Locking and Sealing Hardware ready to be installed into the machine. |
|
2 |
Second Stage Bucket , Drawing No: 314B7169G005 , Including Locking and Sealing Hardware ready to be installed into the machine. |
|
3 |
Third Stage Bucket , Drawing No: 314B7170G005 , Including Locking and Sealing Hardware ready to be installed into the machine. |
|
1. Delivery Time(FCA our factory): 8-10 months after signing the contract and advance payment.
2. Payment:30% of the total after signing the contract as advanced payment ,70% before delivery
3. Guarantee:8000 EOH or one year after delivery.
Regarding other items (shroud segments, Liner, T.P.) we have another sister company which produces these parts. I will check with tem and revert back to you ASAP.
Looking forward to hearing from you more, we remain.
Dear Sir,
Pls quote the following F9 capital parts today.
|
|
|
# |
Description |
Qty. |
Unit |
|
|
Parts For Gas Turbine GE-F9 |
|
|
|
1 |
First Stage Bucket , Drawing No: 314B7168G006 , Including Locking and Sealing Hardware (Set= 92PCS) |
1 |
Set |
|
2 |
Second Stage Bucket , Drawing No: 314B7169G005 , Including Locking and Sealing Hardware (Set= 92PCS) |
1 |
Set |
|
3 |
Third Stage Bucket , Drawing No: 314B7170G005 , Including Locking and Sealing Hardware (Set=92PCS) |
1 |
Set |
|
4 |
Third Stage Shroud Segment , P/NO: 329A3248G004 (Set=32PCS) , Including Shroud Keys (Set=32PCS) |
2 |
Sets |
|
5 |
Fuel Nozzle , Drawing No: 169D3422G012 , Model: GEF9 MS 9001E |
2 |
Sets |
|
6 |
Transition Piece , Type: PG9171 , P/NO: 101E2571G103 |
2 |
Sets |
|
7 |
Liner , Type: PG9171 , Drawing NO: 101E2562G003 |
2 |
Sets |
|
|