No. |
Project Name |
Capacity
(kW) |
Boiler and Turbine configuration |
Evaporation of Single Boiler
(t/h) |
Time of Design |
Remarks |
|
1 |
Indonesia P.T.HENDRATNA
power plant |
1×N4 |
1 |
|
1996.6 |
|
|
2 |
Indonesia WIJAYA board factory power plant |
1×C6 |
1� |
35 |
1997.1 |
|
|
3 |
Indonesia PT.GUNUNG MERANTI wood furniture factory power plant |
1×C6 |
1� |
35 |
1997.1 |
|
|
4 |
Indonesia JAVA paper factory power plant (Stage 1) |
2×C6 |
3� |
35 |
1996.1 |
|
|
5 |
Indonesia JAVA paper factory power plant (Stage 2) |
1×C6 |
1� |
35 |
1998.3 |
|
|
6 |
Bangladesh RAHTM steel factory power plant |
2×C12 |
2� |
75 |
1999.12 |
|
|
7 |
Thailand HSFC 6MW power plant |
1×N6 |
1 |
|
2004 |
|
|
8 |
Indonesia TiFiCO 2x15MW power plant |
2×N15 |
2� |
75 |
2005 |
|