Form of Equipments Cost Breakdown |
|
|
|
|
|
|
|
NO |
Items of Fired Petroleum Coke Fuel 1x130t/h CFB boiler Project |
QTY |
FOB Price in US$ |
I & F Price in US$ |
CIF Price in US$ |
Remarks |
A |
ENGINEERING DESIGN |
|
$41.80 |
|
|
|
B |
MAIN EQUIPMENT (MECH. Fans & Sootblowers) |
|
|
|
|
|
1 |
Combustion System |
|
|
|
|
|
1.1 |
130t/h CFB Steam Boiler |
1 |
$726.00 |
|
|
|
1.2 |
Boiler's Auxiliary System |
1 |
$68.20 |
|
|
|
1.3 |
Dust Palletizing System |
1 |
$74.80 |
|
|
|
1.4 |
Thermal Insulation |
|
$51.70 |
|
|
|
1.5 |
Installing Materials (Valve, Pipe and Pipe Fitting, etc) |
|
$13.20 |
|
|
|
1.6 |
Crane & Hoist |
|
$1.65 |
|
|
|
2 |
Mandatory Spare Parts for 1 Year operation |
|
$9.90 |
|
|
|
3 |
Recommended Spare Parts for 5 (five) years operation |
|
$26.40 |
|
|
|
4 |
Training |
|
$27.50 |
|
|
|
5 |
Commissioning and its required equipments |
|
$44.00 |
|
|
|
|
TOTAL COST |
|
$1,085.15 |
|
|
|