2.PLOT PLAN
The cooling water system will be of twice-through water supply system. The coal will be transported to power plant by road.
The plot plan will be located according to coal yard�?main block—switchyard from south to north in turn. The main block is located in the middle of the plant. Switchyard is located in the north of the main block. The auxiliary production area is close to the west of the main block. it contains: mechanical draft cooling tower, chemical water treatment plant, comprehensive water pump house, office building, maintenance workshop, etc.
The roads in the plant connect with the main block and auxiliary production area in request of the fire-fighting and function. The width of the road around the main block is 6m. The width of the fire-fighting road behind the boiler is 4m. The 4m wide road connects each auxiliary building in the auxiliary area.
The turning radius of the roads will generally be 9-12m. The radius of the roads entering the workshops will be 6m.
The elevation of the proposed power station will be decided after the detailed site conditions are submitted by the owner. The floor level of main block and auxiliary building will be 0.3m higher than outside. The drainage slope will be more than 3-5�?
The organizing drainage will be adopted in the plant. Rain water will be collected by pipeline below the road in plant then discharge. The chemical water, waste water, oil water and coal yard water will be collected and treated before discharging.
The area in the power plant fence is about 19.50 ha. |