    Gas turbine & spare parts   
      GE 9FA 255mw Gas Turbine Generator   
      GE Licensed MS9001E Series Gas Turbine plant   
      42MW GE Gas Turbine Generator   
      PG6581B Gas Turbine Series Generator Plants   
      PG6581B Gas Turbine Set Supply Scope   
      Gas Turbine Spare Parts   
      Gas Turbine Generator Site Inspection   
      Quotationon Used PG6551B gas turbine plant   
      2MW Gas Turbine Generator   
      7mw-Siemens-SGT200-Gas-Turbine-Cogeneration-unit   
      10MW Gas Turbine Generator   
      Used Gas Turbine Generator Plant   
      Technical-Specification-PG6581B-Gas-Turbine   
      Supply-Scope-of-PG6581B-Gas-Turbine   
      Budgetary Cost for 108MW Gas Turbine Plant   
      Siemens Gas Turbine Generator   
    HFO Diesel generator & Marine HFO Engine   
      8x8735kw MAN 18V32/40 HFO Diesel power Proposal   
      8x 4.1mw MAN 9L32/40 hfo power plant proposal   
      10x5.5MW MAN 12V32/40 HFO diesel plant proposal   
      3mw-9mw MAN 18V32/40 HFO Diesel generator   
      6 units 5.5mw MAN 12V32/40 hfo diesel plant   
      3x3.5mw MAN 8L 32/40 hfo diesel generator plant   
      1MW diesel generator    
      1.5MW Diesel Generator Set   
      2M Diesel Generator Plant   
      Sample Diesel Power Plant Proposal 9x2mw   
      Diesel power Plant List   
      Used Diesel Generator   
      Diesel Generator Pictures   
      Bio diesel generator power plant MW   
      Sample Pack List for 10x2MW HFO diesel power Plant   
      10kw-4000kw-Cummins-MTU-diesel-generator-set   
    MTU Cummins Perkins Volvo Diesel Generator   
    Steam Turbine   
      Extraction Condensing Turbine   
      Condensing Steam Turbine   
      Recovery Turbine   
      Extraction Turbine   
      Required Data for Quotation   
      Alstom-Licensed-330MW-Steam-Turbine   
      Quotation-50MW-condensing-steam-turbine   
      Quotation-30MW-Condesing-Steam-Turbine   
    Boiler   
    Power Plant Generator   
      Air Cooled Power Generator   
    Hydro Turbine   
    Engineering Machinery   
      Truck Mounted Crane Crawler   
      Trailer Concrete Pump   
      China Bulldozer   
      China Crane   
      Benz Truck and Lorry from China   
    Cable&Wire   
    Electric Motor   
    Transformer in MVA   
      Germany Certificates   
      Required Data for Quotation   
      Transformer Reference   
      Sample Inquiry   
    Wind Turbine Generator   

Diesel Generator Proposal

Power Plant Proposal

 

Home > Equipments > HFO Diesel generator & Marine HFO Engine - 3x8 l32-40 Technical Program of Kurdistan DG Power plant


 

3x8 l32-40 Technical Program of Kurdistan DG Power plant

 
3x8 l32-40 Technical Program of Kurdistan DG Power plant
 
The Technical Program of HFO Power Station
 
Contents
1.  Company introduction .................................................................................................. .1
2.  Codes and standards................................................................................................... ..1
3.  Environmental conditions ............................................................................................. ..2
4.  Customer Requirements................................................................................................ ..2
5.  Summary of power station............................................................................................. .3
5.1 Overall description of heavy fuel oil power station......................................................... ...3
5.2 Characteristics of HFO power station............................................................................ ...4
5.3 The economy of program about HFO power station ....................................................... .5
6.  Scope of supply......................................................................................................... ...6
7.  Configure of power station system .............................................................................. ...7
7.1 Diesel generating sets ................................................................................................. ...8
7.2 Lubricant system........................................................................................................ ...10
7.3 Lube supply system .................................................................................................... .13
7.4 Coolant system.......................................................................................................... ...14
7.5 Nozzle cooling circulation system............................................................................... ...15
7.6 Cooling water preheating module.................................................................................. .16
7.7 Cooling water supply system....................................................................................... ..16
7.8 Fuel system................................................................................................................ ..16
7.9 Inlet system................................................................................................................ ..18
7.10 Exhaust system ...................................................................................................... ...19
7.11 Leaked oil & decontamination module....................................................................... ...19
7.12 Compressed air system ........................................................................................... ...20
7.13 Electrical equipment of generating sets ..................................................................... ..20
7.14 Architectural equipment............................................................................................. ..23
8.  The practicable contents for the contractor................................................................... .24
9.  Technical data and drawings of products...................................................................... .24
9.1 General requirements................................................................................................... ..24
9.2 Basic Requirements of information presentation........................................................... ..25
10. Progress of production and delivery ........................................................................... ..27
11. Delivery .................................................................................................................... ...28
12. The scope of service protection ................................................................................. ...28
13. Contacts ................................................................................................................... ...29

 
1.  Company introduction
OUR PRODUCTER, founded in 1995, registered capital 185,000,000, headquarter in Yiwu, Zhejiang Province, is an external enterprise specialized in the research and development, manufacturer, sales and service of diesel generators. Because of the products, technique and service of OEM cooperation with German MTU, UK Perkins, South Korea DOOSAN,USA Marathon, France Leroysomer and other world-known enterprises, the emergency electrical stations provided electricity guarantee for Xiangguang Copper(4800KW), Jiangxi Copper Group(3200KW),China Financial Center Database(11000KW),Jiangxi LDK Solar (5600KW),etc.
The factory of Hangzhou, established in April,      2005, is situated in Hangzhou Economic and
Technological Development Zone, with a floor area of 50,402 square meters and the total investment of US$59.6 million. On October 11th, 2006, OUR PRODUCTER signed a license agreement of technology acquisition and collaborative production with MAN Diesel Group to become a licensed member, specialized in producing MAN Diesel high-power, medium speed, four-stroke engines, auxiliaries and propulsion system with the power ranging from 1000kw to 10,000kw. Supervised by the experts designated by MAN Engine Company, the products all passed MAN product quality inspection, Ship Classification Society OF CCS and BV. On June 20th, 2009, the first 32/40 4500KW engine held a ceremony, released to the users and realized the production. The company plans to produce 20 engines in 2009 and 100 engines in 2010. The company dedicated to research and exploration of heavy fuel oil power station, supported by the technology and products of MAN and the over ten-year experience of emergency power station. In May,2009, signing an agreement of the heavy fuel oil power station South American market development, the two sides plan to design, construct and operate Brazil 174Mwand 200MW heavy fuel oil power station, which got technology and supporting services from MAN.
2.  Codes and standards
Equipment, parts and auxiliary equipment, provided by the sealer, correspond with the latest version of the standard, but they are not limited to the following standard:
2.1 State Standards
 
GB2820�?997             《Alternated current drive reciprocating internal combustion engine generating sets�?/DIV>
 
JB/T10303-2001       《Technical conditions of power frequency diesel generating sets�?/DIV>
GB755�?000             《The basic technical requirements of electric rotating motor�?/DIV>
GB1105�?987           《Performance testing method of internal combustion engine housing�?/DIV>
GB1859�?000           《Internal combustion engine noise determination method�?/DIV>
GB3907�?983           《The basic measuring method of industrial radio interference�?/DIV>
JB/T8194-2001         《Vocabulary terms of internal combustion engine electrical station�?/DIV>
GB12699-1990            《Rated power, rated voltage and speed of power frequency diesel generating sets�?/DIV>
CB/T3253-1994          《Technical conditions of marine diesel engine�?/DIV>
CB/T3254-1994          《Experiment of marine diesel engine housing�?/DIV>
GB8840-1988             《Exhaust limits of marine diesel engine�?/DIV>
2.2 Technical standards of MAN
3.    Environmental conditions
Refer to ISO 30461/1-2002
The standard environmental condition
Environmental temperature: 25�?
Barometric pressure: 1bar
RH (relative humidity): 30�?
Fuel oil condition:
 
Fuel lower heating value: 42700 kJ/kg
4.    Customer Requirements
Total capacity of power station: 3x3.5MW
Voltage: 6.3kV
Frequency: 50Hz
 
PF (Power Factor): 0.8pf

 
5.  Summary of Power station
5.1 Overall description of heavy fuel oil power station
There are 3 MAN 8L32/40 diesel generating sets in the heavy fuel oil power station, 2 sets running in parallel 1 stand-by ,each set power: 3860KW
Total power: 11.58MW
Voltage: 6.3kV
Frequency: 50Hz
PF: 0.8pf
Speed: 750rpm.
The design picture of standard electrical station�?/DIV>
 �?nbsp;      Power station
�?nbsp;      Exhaust system and exhaust boiler
�?Sweetener
�?nbsp;      Radiated coolant system
�?Fuel depot
�?Pump station
�?Maintenance workshop and warehouse
The power station contains power station, exhaust system and exhaust boiler, radiated coolant system�?fuel depot, pump station, maintenance workshop & warehouse and working building. Generating sets, auxiliary machines, supply unit, lube filtration separator and control system are all installed in power station. If you don't consider terrain factors influence, the ideal power station can take up an area of 140m?90m. While the actual station design could be adjusted by weather, environment and terrain, but principle of proximity should be considered to prevent too much a long pipe arrangement. At the same time, the heat of heavy fuel oil tank is realized through the vapor of exhaust boiler, so the short line is in favor of heat insulation.
The heavy fuel oil could be the main fuel and light diesel oil the auxiliary fuel. With the main generating sets parallel operation, each unit can input or exit operation. The control system could adjust power balance, power of different sets, which has protective measures of inverse power, over current, etc.
 (Suggestions) The power station need to collocate a 250kVA auxiliary engine, which can supply the black start power, light fuel oil, 24V storage battery start, power -0.4kV, frequency-50Hz, PF-0.8pf, and rotated speed-1500rpm. When the power station comes into good running, the auxiliary engine turns to the emergency standby sets.
Transformer, collocate by power station, provide the main auxiliary equipment with working power supply, the electricity of station lighting and domestic consumption.
5.2 Characteristics of HFO power station
 
(1) Highly-structured corollary equipment, flexible installation site and short construction period
The corollary equipment of heavy fuel oil generating sets is rather simple for little corollary
Equipment, small volume and light in weight. Compared with water turbine-generator set needed to dam, vapor generating set needed to boiler, fuel storage, and water treatment system, the diesel generating set has advantages of small occupation, high construction speed and low invest cost.
Modularity unit system used for heavy fuel oil generating sets, flexible arrangement according to the terrain, which is fit for construction of mountain area and mine area, subjected to small regional terrain restrictions.
(2) High thermal efficiency, low fuel oil consumption and low operation cost
The heavy fuel oil machine extended from diesel is the highest thermal motors of thermal efficiency, of   which the effective thermal efficiency is 40%�?0%, the high-pressure steam turbine is about 20%�?40%, and combustion gas turbine is about 20%�?0%. So fuel consumption is rather low about 178g/kWh. The power station form applied with heat and power cogeneration, has the higher whole energy conversion efficiency, and the thermal power gets more fully used.
(3) The rapid starting and can quickly reach full power
The heavy fuel oil generating sets may use heavy fuel oil and light fuel, which could reach full loaded operation in 3 min of emergent condition (light fuel oil used on emergency ), and in 10 min of normal operation condition (starting uses light fuel oil, and heat engine uses heavy fuel oil ),while the thermal & electricity steam power equipment generally needs 3�?h from starting to full load. What’s more, the shutdown process of diesel is rather short, started and shutdown frequently.
(4) Simple maintenance, small conventional maintenance work, little operation staff, overhaul period of 36000h (related to the fuel oil quality), and low operation expense.
 
(5) Convenient unit combination, capacity easy to extended
 
Each capacity of MAN heavy fuel oil power station generating sets, ranging from 3000kw to
21000kw, which has the advantage of fitting for more power supply load with more selected capacity.
When adopting heavy fuel oil power station generating sets as power, the installed capacity may dispose neatly according to actual need, which can increase power set capacity in the after enlargement & production. The expansion of access is simple and smart, so the expense of primary construction investment is much lower.
5.3 The economy of program about HFO power station
 
�?)Economy of power station operation
a、Fuel cost
MAN 8L32/40 generating sets adopted by this program, the fuel consumption rate is:
 
Rate of loading
100%
85%
Fuel consumption rate of engine
181g/kWh
179g/kWh
Fuel consumption 1kWh of Gensets
187.6 g
185.5 g
 


Estimated with 180# heavy fuel oil, 1600 Yuan\ton

Generator efficiency 96.5%;

The fuel cost of 1kWh

 
Rate of loading
100%
85%
1 kWh
0.3RMB
0.297 RMB
 
b、Oil cost
When lube oil consumption rate is 0.8 g/kWh, generator efficiency is 96.5%, provided by MAN database, the lube consumption is 0.829g/kWh.
c�?Maintenance cost
The heavy fuel oil power station has a long overhaul period that can reach 36000 hours in   general condition. Counted by 20 hours per day it can operate over 5 years continuously.       With a mature model 8L32/40 and low malfunction rate, it is widely used between the ship and power station domain. Also with plenty of spare parts storage and supply, the maintenance cost is rather lower.
 

 
6.  Scope of supply
No.
Designation
Contents
Unit
Qty.
Installed  location of machines
Remarks
1
OUR PRODUCTER-MAN 8L32/40generator,generating sets
 Engine, shaft coupling, public chassis, control panel
set
3
Power plant
2
Auxiliary module
Comprised by lubricating pump, lube oil cooler,   lubricant temperature control valve, lube self-cleaned filter, high temperature pump, high water temperature control valve, low temperature pump, low water temperature control valve, control switch cabinet, etc.
set
3
With standby
3
Lube separating module
Including lube delivery pump, lube preheating device, lubricant separator, sump pump, sump tank, control switch cabinet, etc.
set
3
With standby
4
Fuel supply module
Conversion valve of heavy fuel oil and light oil, fuel meter, viscosity control, fuel mixed tank, fuel pressure pump, HFO end heater, fuel cooler, fuel double filter, control switch cabinet
set
3
with standby
5
Leakage oil &  decontamination module
Sludge pump discharge, fuel leaked oil  tank, lube sludge tank
set
1
6
Engine preheating module
Preheating high temperature water, lubricating oil
set
3
7
Inlet filtration muffler module
Shutter, inlet filter, inlet muffler
set
3
8
Nozzle cooling module
Radiator, centrifugal water pump, cooler, expansion tank, temperature control valve, filling equipment, control switch cabinet
set
3
9
water maintenance module
Radiator, centrifugal water pump
set
1
Pump plant
10
 Heavy oil separation module
HFO delivery pump, HFO preheating device, Separator, sump pump
set
2
11
Air container
Starting air container, working air container, pressure reducing valve
set
2
with sandy
12
Air compressor
H.P. air compressor, L.P. air compressor
set
2
13
Radiator
High temperature water and low  temperature water radiating
set
3
Radiator
14
Exhaust Muffler
Exhaust Muffler
set
3
Outlet and exhaust boiler
15
Exhaust boiler
Boiler body, air manifold, water pump, control switch cabinet
set
1
16
Switch cabinet
Switch cabinet of parallel generating sets
set
3
Power Distribution room
17
Feeder cabinet
Switch cabinet of total outgoing line
set
1
18
Neutral point resistance cabinet
Neutral point grounding of generator
set
3
19
PT cabinet
PT bus couple
set
1
20
DC panel
set
1
21
power distribution cabinet
Power consumers and distributors of each module system
set
1
 


7.  Configure of power station system
Configure of power station system contains as follows:
Diesel generating sets
 
Lube system
Lube supply system
Coolant system
Nozzle cooling circulation system

 
Cooled water preheating module
Cooled water supply system
Fuel system
Inlet system
 
Exhaust system
Leaked oil & decontamination module  
Compressed air system
Electrical equipment of generating set
 
Architectural Equipment(the buyer in charge�?
7.1 Diesel generating sets
The generating sets mainly include diesel, duplex bearing generator, high elasticity shaft coupling and public housing. Diesel and duplex bearing generator are connected by high elasticity shaft coupling, which are also supported and fixed by public housing.
Function of diesel generating sets:
Rated power…�…�…�…�…�…�…�…�…�…�…�3860kW
 Rated speed…�…�…�…�…�…�…�…�…�…�…�50rpm
Rated voltage …�…�…�…�…�…�…�…�…�…�..6.3kV
Rated frequency…�…�…�…�…�…�…�…�…�…��? 50Hz
PF(Power factor)…�…�…�…�…�…�…�…�…�…�…�.0.8
Steady-state voltage adjusting rate…�…�…�…�…�…�…≤0.5%
Transient voltage adjusting rate.................................20%�?15%
Sudden load changing voltage steady time…�…�…�…�. �?S
 Voltage fluctuation rate..................................�?.5%
Steady-state frequency adjusting rate …�…�…�…�…��? �?-0.5%
Transient frequency adjusting rate…�…�…�…�…�…�+10%�?7%
Sudden load changing frequency steady time…�…�…�…�…��?S
Frequency fluctuation rate .................................<=0.5%
Waveform distortion ................................�?%

 
The generating sets as the main electrical power, no limitations for operation time; it can operate and supply electricity continuously except the normal maintenance. In the operation process, the period can permit the overload operation of one hour per 12 hours, and if it overloads 10%, the function of the sets doesn’t fall.
7.1.1 Diesel
 
Brand and model of diesel …�…�…�…�…�…�…�…�…MAN 8L32/40
Pattern ............................................................., L four stroke, direct injection, turbocharger, air cooled, and compressed air starting
Cylinder bore .....................................................320mm
 
Stroke...........................................................................400mm
 
Bore spacing ................................................................ 530mm
 
Compressed ratio ...........................................14.5
 
MCR (Most Continuous Power)\speed…�…�…��? 4000kW/750 r/min
 
Direction of rotation…�…�…�…�…�…�..Crankshaft clock-wise rotation  (as viewed from output end)
 
Lowest steady speed ................................................. 250r/min
 
Fuel consumption rate (When MCR happens)..................181g/kW.h,tolerance+5%
 
MEP (Mean effective pressure) …�…�…�…�…�…�…�..4.9Mpa
 
Pistons mean speed..................................................................10 m/s
 
Air intake flow............................................................................6.8kg/kW.h
 
Exhaust gas flow.......................................7.0kg/kW.h
 
Exhaust gas temperature after supercharger…�…�…�…≤354�?
Supercharger air pressure…�…�…�…�…��?.0.404MPa (Absolute pressure)
Supercharger air temperature before cylinder…�…�…�…�…��?43�?
Exhaust main pipe temperature before supercharger…��?�?65�?
Exhaust temperature of every cylinder …�…�…�…�…�…�…��? �?10�?
Most combustion pressure ............................................19.0Mpa
Diesel inlet lube pressure...................................................0.4�?.5MPa
Diesel inlet lube temperature ....................................... 65�?
 
H.T. water into-machine pressure …�…�…�…�…�…�…��?0.3�?.4MPa
H.T. water out-machine pressure ............................................90�?
Injector coolant water into-machine pressure…�…�. 0.2�?.5 MPa
Injector coolant water into-machine temperature …�…�…�..60�?
Fuel into-machine pressure................................................0.4�?.8MPa
7.1.2 Generator
Brand of generator .................................LEROYSOMER
Generator output power\speed…�…�.......3860kW/750 r/min
Direction of rotation…�…�…�…�…�…Counter clock-wise (as viewed from input end)
 PF..........................................................................0.8
Voltage, frequency ....................................................6.3kV 50Hz
Efficiency..................................................................96.5%
 Grade of Protection....................................... IP23
Winding temperature sensory …�…�…�…� 2x6Pt100 (sensory) (1 set standby)
Anti-freezing heater…�…�…�…�…�…�…�…�…��?.AC230V
Coolant method............................................................................ Self-fan coolant
 
AVR (Automatic Voltage Regulator) …�…�…�…�…�…�Installed on generator
 
7.1.3 High elasticity shaft coupling
Connect the diesel and generator elastically in order to make sure the output power from diesel deliver to generator.
Model..................................................................CRS3420
7.1.4 Public housing
 
Fix and support diesel and generator, internally install lube working oil tank and contain lube for diesel.
7.2 Lubricant system
Lubricant system provides sets with lube of regular flow, temperature and quality, in order to lubricate and cool bearing, operation parts and piston. With separation, filtration and fresh supplement of lube, it can guarantee the function of set lube.
 

Lubricant system is a closed circulation system that connects atmosphere with crankcase breather, as shown in Figure1.
Figure 1: The principle diagram of lubricant system
Lubricant system contains lube working tank, lube oil pump, lube cooler, lube temperature control valve, lube oil filter, lube pressure regulating valve, lube preheating module and lube cleaned separating module, etc.
7.2.1Lube working tank
Installed public housing of generating sets internally. When the generating sets operate, the oil level must be between upper limit and bottom limit of working tank.
Capacity of lube............................................4 m3
7.2.2Lube oil pump
 
Lube oil pump has gear type and screw pump, which can make circulation by the lube. Installed safe relief valve internally to prevent the high system pressure. And lube oil pump drives by motor, one standby one uses.
Flow..................................................................................180 m3/h, 8 bar
7.2.3 Lube cooler
Lube cooler is panel cooler to take accumulated heat of system.
 Heat exchange....................................................................... 680 kW
7.2.4 Lube temperature control valve
Lube temperature control valve uses for maintain the constant temperature of system or the change within the small range of system temperature.
Control temperature…�…�…�…�…�…�…�…�..65�?/DIV>
7.2.5 Lube oil filter
Lube oil filter can protect the diesel, which can keep off the impurity and lies in the entrance of diesel lube oil. Also the lube oil filter is continuous cross flow current kick-type self-cleaned filter.
       Nominal filter fineness…�…�…�…�…�…��?.34μm
7.2.6 Lube pressure regulating valve
Lube pressure regulating valve is to regulate the system power of the operation process, which can make the inlet lube within the certain range of pressure of diesel.
Regulating pressure................................. 4-5bar
7.2.7 Lube preheating module
Parallel connection with the main lube system, it may preheat the lube of working tank to guarantee the rap is starting or sudden load. Generally, high temperature coolant water system and lube oil system are preheated with the same module.
Preheating temperature…�…�…�…�…�…�…�…�…� 40 �?
7.2.8 Lube cleaned separating module
It is connected with the main lube system, very important, which includes lube delivery pump, lube preheating unit, lube separator, sump pump, sump tank, and control switch cabinet. Generally, it separates the moisture and harmful of lube oil dust with centrifugal oil separator.
Effective handling capacity…�…�…�…�…�…�…�…�2.25 m3
7.3 Lube supply system
Lube supply system provide system with accepted, storage and full lube to make the continuous operation of power station. The new lube is supplied by oil can or tanker truck. Then the workers can fill the tank of every lube working tank.
Figure 2: The principle diagram of lube supply system
Figure 2 is lube supply system including baggage hold oil of lubricant unit, lube storage oil can, lube delivery pump, lube capacity gauge, etc.
7.3.1The unloading oil unit of lubricant system
This unit mainly contains unloading oil pump, valve and granular filter. The unloading oil pump is gear type or screw pump that provides lube into storage tank from oil can or tanker truck, and drives by motor, one standby one uses.
The unloading oil flow…�…�…�…�…�…�…�..25 m3/h�?bar (one standby one uses)
7.3.2Lube storage tank
 
Arranged in the oil house, heated by the steam and the normal operation of power station, the oil level must be between upper limit and bottom limit of working tank.
      Capacity of lube storage tank…�…�…�…�…�…�…�…��?5 m3
7.3.3 Lube delivery pump
This unit is gear-type pump with the main function of delivering the lube oil of oil tank to the working oil tank, which drives by motor, one standby one uses.
Delivery pump...........................................................15 m3/h�?bar (one standby one uses)
7.4 Coolant system
Coolant system, divided into two-closed circulation system, the low temperature water circulation system and high temperature water circulation system connect the atmosphere with the expansion radiator. Excepted from cooling the main machine, it needs to guarantee    the  proper  temperature  of  the  engine  to  meet combustion   demand   different   load.   The   low temperature water is responsible for cooling supercharge Air II and lube oil, while the high temperature water for cooling cylinder jacket, supercharge Air I and cylinder head. And the external cooling uses the radiator not adding water.
     Figure 3: The diagram of coolant system
The low temperature water circulation system and high temperature water circulation system include expansion radiator, water pump, radiator and temperature control valve.
7.4.1 Expansion radiator
Expansion radiator compensates the heat expansion of high temperature water system and high temperature water circulation system which has the effect for compensating water and releasing air.
      High temperature expansion radiator…�…�…�…�…�…�…�…�..250 L
Low temperature expansion radiator…�…�…�…�…�…�…�…��?250 L
7.4.2Water pump
Both high temperature water pump and low temperature water pump are all centrifugal water pump, driving by the motor, one standby one uses. High & low temperature water pump deliver high temperature water and low temperature water separately through pump, making the circulation in the return line of their own.
High temperature water pump flow …�…�…�…�…�.108m3/h, 5 bar
 Low temperature water pump flow…�…�…�…��?.180m3/h, 4.5 bar
7.4.3 Radiator
The low temperature radiator is responsible for cooling supercharge Air II &lube oil and drop off the heat of nozzle, while the high temperature radiator for cooling cylinder jacket, supercharge Air I and cylinder head.
High temperature heat release…�…�…�…�…��?.3020 kW
 Low temperature heat release…�…�…�…�…��?2495kW
7.4.4Temperature control valve
The main function of high temperature water temperature control valve is to keep the constant temperature of out-let high temperature water, while the low temperature water temperature control valve is to keep the constant temperature of in-let low temperature water.
High temperature water temperature control valve …��?.90�?
Low temperature water temperature control valve…�…�..decided by the local conditions
 
7.5 Nozzle cooling circulation system
 
Cool the nozzle as burning the heavy fuel oil. Nozzle cooling circulation system is a closed forced circulation system for cooling nozzle and taking heat by low temperature water system .Nozzle cooling circulation  system mainly contains radiator, centrifugal water pump, cooler, expansion radiator, temperature control valve and compensating water unit, forming the nozzle coolant module with all the equipment.
Figure4:   Nozzle cooling circulation system
 
Heat exchange............................................35kW

Water flow...............................................3.2 m3/h�?.0bar

 
7.6 Cooling water preheating module
Parallel connection with the main high temperature coolant water system, this unit preheats the cooled water in sets and pipe to guarantee the rapid starting and sudden load of engine. Generally, high temperature coolant water system and lube oil system are preheated with the same module
Preheating temperature…�…�…�…�…�…�…��?40 �?
7.7 Cooling water supply system
The main function of cooling water supply system is to supply and storage cooling water to meet the water consumption of boiler system, guarantee the normal operation, has the function of softening and dealing with raw water. The cooling water supply system includes softening equipment, radiator and centrifugal water pump.
 
Systematic radiator…�…�…�…�…�.20 m3
Water supply pump ..............6m3/h, 3 bar (one standby one uses) Water softening equipment
 
7.8 Fuel system
Fuel system includes the parts of unloading oil, storage, delivery, handling, supply and gather of return oil, whose functions are to supply fuel continually to diesel and to preserve the constant flow, pressure, cleanness and viscosity. The heavy fuel oil system has the light oil as standby use, when starting and shutdown changing to light oil supply. Fuel system includes heavy unloading fuel oil unit, heavy fuel oil storage oil-can, and heavy fuel oil  delivery unit, heavy fuel oil buffer oil cabinet, heavy fuel oil separating module, daily heavy fuel oil cabinet, fuel supply module, oil sludge tank, diesel unloading oil unit and daily diesel cabinet.
Figure 5: The diagram of fuel system
7.8.1Heavy unloading fuel oil unit
This unit mainly contains unloading oil pump, valve and granular filter. The unloading oil pump is gear type or screw pump that provides heavy fuel oil into storage tank from tanker truck through pump, and drives by motor, one standby one uses.
Unloading oil flow..................................70 m3/h�?bar
7.8.2Heavy fuel oil storage oil-can
Arranged in the oil house, heated by the steam and with the normal operation of power station, the oil level must be between upper limit and bottom limit of working tank.
Capacity of heavy fuel oil storage oil-can…�…�…�…�…�800 mheated by the steam Oil-cans can make 3 machines use 14 days
7.8.3Heavy fuel oil delivery unit
Heavy fuel oil delivery unit has gear type and screw pump, with the main function of delivering heavy fuel oil from storage oil-can to buffer oil cabinet by pump, which drives by motor, one standby one uses.
Delivery pump flow…�…�…�…�…�…��?.35m3/h�? bar (one standby one uses)
7.8.4Heavy fuel oil buffer oil cabinet
Arranged in the oil house, heated by the steam and with the normal operation of power station, the oil level must be between upper limit and bottom limit of working tank.
Capacity ................................., , , ........................................110 m3         ,       heated by the steam
7.8.5 Heavy fuel oil separating module
This unit, very significant, filtrates the heavy fuel oil with separator, which includes heavy fuel oil delivery pump, heavy fuel oil preheating unit, separator, oil sump and switch control cabinet. The separating impurity is delivered to oil sludge tank by pump.
Effective handling capacity…�…�…�…�…�…�…�..20 m3/h
7.8.6Daily heavy fuel oil cabinet
Arranged in the oil house, heated by the steam and with the normal operation of power station, the oil level must be between upper limit and bottom limit of working tank.
Capacity .................................................................................. 220 m3
7.8.7Fuel supply module
The main function of this unit is to heat and pressure fuel filtration, to supply the diesel fuel under the circumstance of standard temperature, pressure, viscosity and flow, and to realize the transfer between heavy fuel and light oil. This can change into the light oil between the starting and shutdown. Fuel supply module includes conversion valve of heavy fuel oil and light oil, fuel meter, viscosity control, fuel mixed tank, fuel pressure pump, HFO end heater, fuel cooler, fuel twin filters, and control switch cabinet.
    Fuel pressure pump................................. 2.7 m3/h, 8 bar(one standby one uses�?/DIV>
    Fuel twin filters.................................. 34μm
Fuel mixed tank .......................................70 L
7.8.8 Oil sludge tank
Oil sludge tank, heated by vapor of sludge tank, is used for storage impurity, oil sludge and oil residue after the heavy fuel oil separated.
Capacity of oil sludge tank…�…�…�…�…�…�…�. 5 m3
7.8.9 Diesel unloading oil unit
This unit mainly contains unloading oil pump, valve and granular filter. The unloading oil pump is gear type or screw pump that provides heavy fuel oil into storage tank from tanker truck through pump, and drives by motor, one standby one uses.
Unloading oil flow..................................11.52 m3/h�?bar
7.8.10 Daily diesel cabinet
Arranged in the oil house, playing the role of daily working oil tank and storage diesel, and with the normal operation of power station, the oil level must be between upper limit and bottom limit of working tank. It needs to be heated by the steam in winter
Capacity of daily diesel cabinet …�…�…�…�…�…��?100 m3
7.9 Inlet system
Air  inlet  comes  into  the  cylinder  of  main machine  after  turbocharged,  to  prevent  the machine  weary  and  clean  air.  Muffler is generally installed between turbocharger and air filter, which can reduce the high-frequent noise produced by the turbocharger. The inlet system contains shutter, inlet filter and inlet muffler, which forms the inlet filtration muffler module     Figure with each equipment combined.
6: Diagram of inlet system
 
Air flow............................................... 30.5 t/h
Inlet muffler.................................................30dB (A)
7.10 Exhaust system
The burned exhaust gas is pushed out by turbocharger, the temperature from 300�?to 335�?depending on the load of engine and used fuel. Before push put exhaust gas, it is recovering waste heat first by the muffler, then by the exhaust boiler. If needed, the second exhaust cleaned system, such as desulphurization equipment, is also installed. The exhaust system includes exhaust muffler, exhaust boiler and desulphurization equipment.
Figure 7: Diagram of exhaust system
7.10.1 Exhaust muffler
 
Function: Reduce the exhaust noise of engine.
Exhaust flow............................................ 66.6 t/h
 
Exhaust muffler.........................................25 dB (A)
7.10.2 Exhaust boiler
Function: Exhaust energy circulation use for heat of heavy fuel oil, water and lubricating oil, heat tracing, containing exhaust muffler, boiler body, air manifold, water pump and control switch cabinet.
         Evaporation capacity…�…�…�…�…�…��?.5 t/h
Pressure................................................................9 bar
Temperature.......................................................175�?
 
7.11 Leaked oil & decontamination module
This unit includes fuel leaked oil tank, lube sludge tank, sludge pump and exhaust oil pump, with function for collecting leaked fuel then supplying heavy fuel oil separating module. The lube oil sludge separated by the unit delivers to the oil sludge tank. Also, the oil sludge separated by heavy fuel oil separating module delivers to the oil sludge tank through the leaked oil pump.
Sludge and exhaust oil pump …�…�…�…�…�1.8 m3/h�?bar      (one standby one use)
Fuel leaked oil tank........................................750 L    heated by the steam
Lube sludge tank..............................................750 L    heated by the steam
 
7.12 Compressed air system
Compressed air system mainly contains starting air container, working air container, pressure reducing valve and air compressor.
7.12.11 Starting air container…�…�…�…�…�…�.Quantity: 2
Capacity ............................................................ 1000 L, 30bar
7.12.2 Working air container…�…�…�…�…�…�.Quantity: 1
Capacity .....................................................500 L, 10bar
7.12.3 Pressure reducing valve…�…�…��?.…Quantity: 2  
Capability........................................................... 30-7bar
7.12.4 Air compressor…�…�…�…�…�…�..Quantity: 2
              Capability............................................ 30bar, 52 m3/h
 
7.13 Electrical equipment of generating sets
Medium voltage switchgear mainly includes switch cabinet of generating sets, feeder switch cabinet and Neutral point resistance cabinet.
7.13.1 Switch cabinet of generating sets
 
Cabinet.............................................................. KYN28-12
 
Dimensions...............................................................800(W)X500(D)X200(H)mm
 
Breaker................................................................VS1circuit breaker 7.2kV�?30A�?-pole 15kA
Draw out type circuit breaker
Protection.............................................................PWZB
Quantity............................................................3side
7.13.2 Feeder switch cabinet
 
Cabinet.......................................................... KYN28-12
 
Dimensions............................................................ 800(W) X500(D) X200(H)mm
 
Breaker...............................................................VS1 circuit breaker 7.2kV�?000A�?-pole 15kA

 
Draw out type circuit breaker
Protection............................................................PWZB
Quantity............................................................1 side
7.13.3 PT cabinet
 
Cabinet............................................................... KYN28-12
Dimensions.........................................................800(W) X500(D) X200(H) mm
 Quantity..........................................1 side
7.13.4 Neutral point resistance cabinet
Dimensions.................................................800(W) X500(D)
X200(H)mm Color .................................................................Camel gray
Quantity................................................................3side
7.13.5 Power distribution cabinet
Dimensions......................................................800(W) X500(D)
X200(H)mm Color ..................................................Camel gray
Quantity...........................................................1side
7.13.6 Control panel of generating sets
Dimensions........................................................... 800(W) X00(D)
X200(H) mm Color ...................................................Camel gray
Quantity....................................................3 sides
Containing control switch, controller, control relay, sensory and alarm display window, etc. Control function
Engine speed regulator
Digital synchronization & load control
Automatic voltage regulation
Voltage monitoring
Frequency monitoring
Breaker chain
Breaker closing
Breaker tripping
Engine auxiliary module control
Engine starting and shutdown
Alarm display window
Generator control panel displayed the parameter of shutdown and alarm related to electricity and machinery. The parameter of shutdown comes from hard-wired contact end voltage of engine protection system, while the alarm settings is produced by the analog signal from installed sensory according to the main control module. The company can provide different kinds of sensory, such as 4-20mA and PT100.
The displayed alarm & shutdown parameter as follows:
 
Indicator light of control power supply
Indicator light of engine starting malfunction
Indicator light of emergent shutdown
Engine over-speed indicator light
High engine temperature
High engine oil temperature
Engine coolant level
Low oil pressure
 
Differential malfunction
 
Generator over-current
 
Grounding malfunction
Loss of voltage \ over-voltage
Reverse power
Loss of magnet
 
High winding temperature
 
High bearing temperature
High temperature of exhaust pipe
High temperature of exhaust
Low fuel oil level

Low temperature of coolant
Regulator malfunction
Monitor of metal particles in oil pan
Malfunction of lube treatment facility
7.13.7 Direct current cabinet
Dimensions....................................................800(W)X600(D)X2200(H)mm
Quantity........................................................1 side
AC input voltage........................................ AC 400V±5%�?0Hz,three phase four wire system,two input electrical power
DC Output Voltage ................................ DC220V (Working  voltage  of  auxiliary  switch cabinet)
Battery capacity..................................... Plum bionic acid battery non-maintenance 100Ah
Precision of voltage regulation…�…�…�…�…�…�…�.. ≤�?.5%
Precision of steady current…�…�…�…�…�.≤�?.5%
Ripple factor..........................................................≤�?.5%
System efficiency..................................�?0%
 Power factor (PF)............................................. �?.92
Operation noise ......................................................�?0dB
Dielectric strength.........................................2000V/min no flashover, no disruption
Grounding resistor............................................... �?.1Ω
Output return circuit................................. Standard configuration: KM 5, HM 5.
Cabinet structure ...................................................Product  screen body  of  our  company adopt  PK structure, the front with glass doors
Grade of Protection.................................IP30
 
7.14 Architectural equipment
Architectural equipment includes infrastructure, power plant, pump plant, maintenance workshop, basic equipment, frozen soils construction referred to local environment and detailed construction schedule,

 
subsequently communicated among the buyer, designing institute and the sealer.
8.  The practicable contents for the contractor
 
No.
Contents
Remarks
1
The whole design of power station
Project  design  satisfied for local environment
2
Construction project, equipment foundation construction
3
Units in place
4
Installation of power station equipment
5
Pipes (oil pipe, water pipe, air pipe, smoke pipe, tracing pipe, etc.)
6
Oil tank& construction
7
heavy fuel oil, diesel oil, lube unloading oil equipment
8
Unit station service transformer, generator transformer, electricity transmission
9
Cable, wire, bridge
10
125kVA auxiliary machine
9.  Technical data and drawings of products
 
9.1 General requirements
9.1.1 The data provided by the sealer should be the national legal system of units, ie International System of Units, language be Chinese, the foreign drawings and files of import parts be provided foreign original documents. The sealer will provide the whole information and drawing according to units technical specifications, technical requirements, scope of supply and guaranteed conditions.
9.1.2 The drawings offered by the sealer should be clear and micro-copied drawings are forbidden to be offered. The organization structure of data is to be clear and strict in logic. The content of data must be correct, accurate, clear and comprehensive, meeting the project.
9.1.3 The sealer should provide the data related with the equipment design in time.

 
9.1.4 If to be found, the sealer will provide the files and data free of charge to other data not lined in the contract but project to be needed. When the equipment makes an improvement, the sealer will provide the new technical data free of charge in time.
9.2 Basic Requirements of information presentation
 
9.2.1 Technical files of coordination with project design data and drawings
The sealer will provide the data and drawings satisfied for the project design, project installation and operation maintenance.
As shown below:
 
No.
Designation
Qty.
Submission time
Remarks
1
Unit profile, unit installation system drawing,   drawings   of   external auxiliary  equipment  and  connection dimension, installation drawing
1
In one half a month after contract signing
AUTOCAD E-document
2
The  basic  reference  diagram  of generating sets
1
In one half a month after contract signing
AUTOCAD E-document
3
Reference diagram of power plant
1
In one half a month after contract signing
AUTOCAD E-document
4
Principle diagram of system electricity,switch  cabinet(one  or  two  return circuit, chain, signal return circuit and external contacts )
1
In one half a month after contract signing
AUTOCAD E-document
5
Switch   cabinet, outlet cabinet installation and connecting diagram
1
In one half a month after contract signing
AUTOCAD E-document
 

 
9.2.2 The technical files as data and diagram delivered with equipment
 
The sealer shall provide the needed data and diagram satisfied for the project installation,
pre-commissioning,  performance acceptance and operation  maintenance in time (rather than the following files).
 

No.
       Designation
       Qty.
       Submission time
Remarks
1
       Drawings  of  unit  profile,  external auxiliary  equipment  and  connection dimension, installation drawing
One set per set
Delivered with the equipment
 
2
Principle diagram of system electricity,switch  cabinet    (one  or  two  return circuit, chain, signal return circuit and external contacts )
3
Diagram of units control system
4
Diagram   of    external    auxiliary equipment control system
5
Switch   cabinet,  outlet      cabinet installation and connecting diagram      
6
Installation operating instructions
7
Operating instructions
8
Maintenance instructions
9
Atlas of spare parts
10
List  of  spare  parts  about  operation maintenance and loss
11
List of equipment packing
12
certification by manufacturer

 
10. Progress of production and delivery
 
PT
Scheduled plan of HFO power station project
No.:ZGZD
Edition\modification�?009/ 0
Effective date�?/DIV>
NO
Period of time
project name
20xx
20xx+1
Jan
uary
Febru
ary
Mar
ch
April
May
June
July
Aug
ust
Septe
mber
Octo
ber
Nove
mber
Dece
mber
Janu
ary
Febr
uary
March
April
May
June
July
1
Contract signing
-------�?/DIV>
2
Engine scheduling
------------------------------------------------�?/DIV>
3
 Purchase  of  generator and auxiliary equipment Unit production and test
----------------------------------------�?/DIV>
4
delivery
-----�?/DIV>
5
Delivery  of  unit  and auxiliary equipment
---------�?/DIV>
6
Equipment installation
-----�?/DIV>
7
System debug
----�?/DIV>
8
Operation training
---�?
 
11.1 Delivery requirements
 
The buyer is responsible for delivering the equipment and insurance for transportation expenses.
 
11.2 Package requirements
The sealer is in charge of equipment package, the package costs included in the total amount. The package and delivery be in accordance with the specifications of GB191-73 pictorial markings for handling of packages.
11.3 Place of delivery
Place of delivery in the sealer’s factory, the buyer should recognize the dispatch goods with the sealer helping to provide truck loading.
11.4 If the damage and loss happen to the equipment in transportation, the sealer will negotiate with the carrier and claim for compensation.
12. The scope of service protection
 
12.1 Warranty period
Warranty period under scope of supply is one year. In the warranty period, the second party is in charge of free, for the problem of building in quality produced by the defects in equipment manufacture. After the warranty period, the sealer provides the technical consultation free of charge and the spare parts at the best price, also responsible for the life-long maintenance.
12.2 Guarantee of field service
In the warranty period, the sealer could provide more timely and comprehensive service guarantee. The spot service engineers sent by OUR PRODUCTER are for the after-sales guaranteed work and train the spot operation workers, with food and accommodation provided by the buyer.
12.3 Technical training to provide the training service free of charge
The sealer can provide the training of five days for ten persons, with food and accommodation provided by the buyer.
12.4 Installation of on-site guidance and commissioning
 
The sealer is responsible for the installation of equipment and commissioning; while the buyer is for solve the just requirements of the spot service engineers in order to ensure all tasks are carried.
 
12.5 Commitment
12.5.1 The aptitudes for spot service engineers of the sealer as follows:
a、Compliance with law, each rules and regulations on site.
b、In place on time with strong enterprise and responsibility.
c、Knowing about the equipment design in contract, familiar with the structure, having the spot     working experience of the same or similar unit, able to do the spot guidance work correctly.
d�?Healthy for the condition of field work.
12.5.2 The responsibilities of the spot service workers
a、The tasks mainly include the processing about problems of equipment quality, guidance for    installation and commissioning, participation in trial running and acceptance functional test.
b、Before installation and commissioning, the technical workers should speak clearly to the
buyer, explained and demonstrate the procedures and methods to be going.
c、The service workers have the right to dealing with all the problems of technology and      business, ie, the service workers have to resolve the problems within the time allowed by the buyer, if the quality problems happen. If the sealer entrusts the buyer resolve the problem,       the spot service workers of sealer must have the power of attorney and afford the related      economic responsibility.
d、Pre-negotiation to the buyer about the normal come& go and change of the spot service workers.
12.5.3 The obligations about the buyer
Coordination with the works of the spot service workers and provision with the convenience for life, transport and telecommunications.
The buyer evaluates and recognizes the writing reasonable suggestions, and if the bad result happens for no execution of the buyer, it’s for buyer's account.
13.   Contacts
 
Both parties will agree in the contract execution stage about the plan, time, place, and contents of  contacts.
 