China National Electric Wire&Cable Imp./Exp. Corp  BBS  Email&MSN: ycl1227@163.com
  
Homepage   |   Power Generation   |   Project Financing    |   Equipments   |   Transmission   |   News   |   Contact    |   services   |   download   |   sitemaps   |   Business Opportunity   |   BBS-Blog   |   Purchasing-agent   |   Exchange Link  

Mail List

E-mail:

Power Generation
    Big Power Plant Projects   
    GE Gas Turbine Power Plant Project   
    geothermal power plant   
      Work Scope   
      Design Data   
      Steam Turbine   
      Cooling System   
      Water System   
      Ventilation   
      Instrumentation Auto.   
      Electrification   
    Diesel power Plant   
    waste heat recovery power plant   
      4.5MW Waste heat recovery 2500t/d Cement Line   
      7.5MW Waste heat recovery 2x2500t/d Cement Line   
      9MW Waste heat recovery 5000t/d Cement Line   
      18MW Waste heat recovery 2x5000t/d Cement Line   
      Technical Proposal of 9MW Recovery Plant   
      Power Plant Connection and Main Equipments   
      Main Equipment Recovery Plant   
      Power Plant Construction Schedule   
      China Reference List waste heat Plants   
      Preliminary Proposal for Cement Plant   
    Thermal Power proposal   
    Questionnaire for Gas/HFO/Liquid Fuel Power Plant   
    Check-List-for-quotation-on-power-plant   
    Power project reference   
      Thermal plant List   
      Foreign Small plant   
      Reference of Sinomach   
      Diesel generator plant list    
      waste heat recovery power plant list   
      Gas Turbine Power plant Reference   
    Indicative quotation of 2x50MW coal fired plant   
    Estimated Quotation for Plant   
    Biomass-Gasification-Power-Generation-System   
    Gas Engine Generator power plant   
    Solar-Panel-Power-Plant-Quotation   
    Power Plant Auxiliary   

Diesel Generator Proposal

Power Plant Proposal

 

Home > Power Generation - Technical Documents 1x200 MW COAL FIRED POWER PLANT/CHEMICAL WATER TREATMENT SYSTEM


 

Technical Documents 1x200 MW COAL FIRED POWER PLANT/CHEMICAL WATER TREATMENT SYSTEM

8  CHEMICAL WATER TREATMENT SYSTEM

Chemical water treatment system includes the following subsystem:
1)  Boiler make-up water treatment system
2)  Chemical dosing system
3)  Water & steam sampling and analyzing system
4)  Industrial waste water treatment system
5) Circulating-water dosing system
6)  Laboratory

8.1          Boiler Make-Up Water Treatment System

The water to be treated is from river water. According to the demineralized water quality requirement of the plant, the water treatment system process will be as follows:
Water from water supply ® clarified water tank ® clarified water pump ®multimedium filter® activated carbon filter ® cation exchanger ® decarbonator ®intermediate water tank ® intermediate water pump ® anion exchanger ® mixed-bed exchanger ® demineralized water tank ® demineralized water pump ® plant user
According to the total loss of the plant, the capacity of the water treatment system is 20t/h, adding to the self-used water, the capacity of the water treatment equipment is 22t/h.
The demineralized water at the outlet of the mixed bed will conform at all times as follows:
Conductivity (at 25°C) �.2ms/cm
Silica                 â‰?0μg/L

8.2          Chemical Dosing System

In order to maintain the pH value and protect the feed-water pipe and equipment from corroding, the design proposes a set of ammonia dosing device including two(2) tanks and two(2) metering pumps for feed water.
In order to remove the oxygen within the feedwater, hydrazine as oxygen scavenger is fed continuously into boiler feedwater line. The hydrazine dosing device including two(2) tanks and two(2) metering pumps.
A phosphate dosing system including two(2) tanks and two(2) metering pumps will be designed to protect the boiler from scaling and corroding.

8.3          Water & Steam Sampling and Analyzing System

In order to monitor quality of water and steam cycle and ensure safety operation of unit, each unit will set one (1) water & steam sampling and analyzing device. Water and steam sampling and analyzing system includes high-temperature cooling rack and low-temperature instrument panel.

8.4          Industrial Waste Water Treatment System

The regeneration waste of the water treatment plant, and acid washing, the cleaning water of air pre-heater etc., are drained to neutralized water basin .The waste water will be discharged when pH reaching 6~9 after neutralizing treatment .

8.5          Circulating-Water Dosing System

8.5.1              The Killing Biology System
For prevent the microorganism growth in the circulating water system, one set of circulating-water killing biology system will be provided. The Main Equipment: Two (2) chemical solution tanks, Two (2) dosing pumps. The Equipment is in the circulating-water dosing room.
8.5.2              Inhibitor dosing system
One set of circulating-water inhibitor dosing system will be provided. The Main Equipment: Two (2) chemical solution tanks, Two (2) dosing pumps. The Equipment is in the circulating-water dosing room.

8.6   Laboratory

One set of instrument and equipment for chemical laboratory will be provided for the water, and coal analyzing.
 