Summary Briefs on the equipment: | 40MVA Power Transformer 变压�?Please find following quotation for the Transformers:
1.Type:1×31.5/40 MVA 132/11.5 kV Transformer
Unit price: (FOB DALIAN, CHINA)
Note:
1. Routine test (according to IEC60076) had been included in the price and will be tested at
LEEEC factory.
2. Tap changer of power transformer we proposed made by MR.
3. The fans, radiators are made by Chinese brand.
4. The price exclude spare parts and supervision of installation at site for engineers from
manufacturer.
5. This price valid will be 20 days from submission of bid offer.
6. Supervision services during installation, testing, commissioning should be paid 200 USD
per man-day for technician and 300 USD per man-day for engineer (Excluding visa fee,
flights fee, accommodation , and quarantine fee).
7. The engineers�?food and accommodation cost (in Liaoyang city) for FAT in LEEEC is not
included in the quotation.
8.The term of payment is T/T.
9. Delivery time is 8 months after Design approval by client and advance payment received by
LEEEC under the condition of FOB Chinese seaport.
10. Warranty Period: 12 months after transformer commissioning or 18 months after
transformer delivery from factory, whichever occurs first. |