TECHNICAL (ENGINEERING AUDIT-BORESCOPE) SERVICE CONTRACT
Contract No:. GT-insepction-BD-200911
PARTIES
1. Venture Energy xxxxxx
2. Leda Greenpower Beijing Trading and Engineering Company Limited, is an EPC and partner of GE-certified supplier of GE gas turbine generator and GE gas turbine spare parts, with its head office located at Rm.803, Building D, Shengshijiayuan Langjiayuan, 98 Jianguo Rd. Beijing, China 100022 (hereinafter referred to as "LEDA").
This Contract is made and negotiated by and between XXX, and LEDA, concerning the Technical Inspection of GE PG6541 gas turbine located in xxxxx (hereinafter referred to as "Site") under the following terms and conditions:
Article 1 Scope of Work
Scope of work of LEDA/XXX for this Particular Project of Bhola Rental Power Plant:
1.1 To perform visual inspection for external components and auxiliaries only on gas turbine base
1.2. To conduct a detail borescope inspection for the hot gas path zone
1.3. To prepared and submit to detail report on
i. Condition of the external components and auxiliaries mentioning there present health, diagnosing of any suspected problem if any, suggestion on reamed including list of required spare parts.
ii. Detail report on borescope inspection mentioning internal health of the unit suggestion on CI and HGPI intervals.
1.4. To prepare and submit a list of spare parts in detail segregated for
i. Combustion inspection
ii. Hot gas path
iii. Emergency/ Consumables
iv. Major overhauling / capital spares (if required)
Preliminary Schedule of the inspection:
Some information about boroscope inspection as below:
We plan to dispatch 4 persons to operate this project, they will stay on site for 3 days. We estimated that it needs 1 week for their passports to be visaed.
The inspected gas turbine should be power off on the eve of our air plant flying off China. We will arrive site in the afternoon of next day, and start work on the 3rd day.
Work on site:
3rd day: Move the borehole plug on casing, part of fuel nozzle, and manhole door on exhaust plenum. Inspect borescope at the same time.
4th day: Continue to inspect borescope, and restore the equipments dismantled.
5th day: Start gas turbine to base load, and examine auxiliary system operation condition.
6th day: Leave site to Dhaka.
Manpower needed : 3-4 labors
Tools needed: usual spanner, manual angle grinders and electric welder.(The latter two tools will be needed in dismantling and restoring mandoor of exhuast plenum)
Article 2 Both Parties' Responsibility and Liability
2.1 LEDA will provide the borescope for extruding photos, monitor for displaying etc if required. XXX will provide all general tools and manpower locally.
Article 3 Price and Payment
3.1 As discussed and agreed by both parties the lump sump payment for the above mentioned of the work is US$ 22,000/- (US Dollar Twenty Two Thousand only) as sues this contract was singed and confirmed through by email transaction.
3.2 All payments will be made by Irrevocable Letter of Credit or by T/T on bank suggested by LEDA on the following terms and conditions:
3.2.1 Only after payment has been received by LEDA that the inspection will be conducted by LEDA.
Article 4 Language and Standards
4.1 All correspondences, data and documents, the technical service reports and drawings prepared by LEDA shall be in the English.
4.2 Measures shall be written in the metric system.
Article 5 Governing Law
5.1 The construction, validity and performance of this Contract shall be governed by the laws of the Government Republic of xxxxx.
Authorized Representative’s signature:
__________________________________
Executive Director
XXX:
Address:
E-mail:
Date: _____________________________.
Authorized Representative’s signature:
___________________________________
…�…�…�…�..
LEDA: Leda Greenpower Beijing Trading and Engineering Company Limited
Address: Rm.803, Building D, Shengshijiayuan Langjiayuan, 98 Jianguo Rd. Beijing, China 100022
Telephone: 0086 10 64714025 Fax: 00861084568952
Date: ______________________________.
quotation:
1. Project: HGPI of one set of PG6541B gas turbine
2. Inspection duration: Twenty (20) days and Eight (8) hours per day
3. Service options
3.1 Option 1: Seller will provide technical supervision
3.1.1 Service of engineer and skilled worker and costs(US dollars)
No. |
Specialty |
Qty |
days |
Unit price |
Total price |
Remark |
1 |
Technical leader |
1 |
20 |
920 |
18,400 |
|
2 |
Engineer |
1 |
20 |
575 |
11,500 |
|
3 |
Skilled worker |
2 |
20 |
517.5 |
20,700 |
|
4 |
Worker for lifting
goods |
1 |
20 |
345 |
6,900 |
option |
5 |
Welder |
1 |
20 |
402.5 |
8,050 |
option |
6 |
Interpreter |
1 |
20 |
230 |
4,600 |
|
|
Sub-total |
/DIV> |
/DIV> |
/DIV> |
70,150 |
|
7 |
International tickets |
7 |
/DIV> |
1725 |
12,075 |
|
|
Total |
/DIV> |
/DIV> |
/DIV> |
82,225 |
|
3.1.2 If duration prolongs due to Buyer' cause, Buyer should give compensation for Seller, according to above-mentioned unit price and days.
3.1.3 Boarding and lodging, local transportation, immigration related fees will be born by Buyer free of charges.
3.1.4 All of tools, crane, spare parts and material consumption will be provided by Buyer.
3.2 Option 2: HGPI will be done by Seller himself
3.2.1 Total personnel are approx. 20.
3.2.2 Price: US Dollars One hundred Eighty Nine Thousand and Seven hundred Fifty USD only (USD189,750). It includes international tickets, wages, visa, insurance, profit and tax etc.
3.2.3 Boarding and lodging, local transportation, immigration related fees will be born by Buyer free of charges.
3.2.4 All of tools, crane, spare parts and consumption will be provided by Buyer.
4.Due to that it is very difficult or complicated for tools for HGPI transport from China to foreign nation and vice verse; so Seller suggests Buyer provide tools for HGPI according to tool list provided by Seller. If there are not in Bangladesh, you can procure from China; Seller can help Buyer to procure.
|