Home > Used Equipment - 3 x NEW GE MS9171E Trifuel for sale


 

3 x NEW GE MS9171E Trifuel for sale

3 x NEW GE MS9171E Trifuel
 
1. Tri Fuel Technology, Standard Combustors capable of Natural Gas, Diesel and HFO operation with water injection skids for NOx control.
2. Andritz Hydro/Elin Austria 50 Hz Static Excited, Air Cooled Generators
3. Dedicated Wash Skids 1 per GT capable of simultaneous fully automated turbine/compressor washing for HFO ops
4. Air Inlet Filters consist of high performance synthetic design and EVAP Coolers.
5. Majority of interconnecting piping, electrical and I&C materials are included in GE Scope and provided.
6. Liquid Fuel Inlet Filters: HFO and Diesel/LFO inlet filters are duplex washable mesh type i.e. No Paper Element Fuel Oil Filters, moreover HFO inlet filters are self cleaning type.
7. State of the Art GE Mark VIe Turbine Controls allow for fuel changeover from Gas to Diesel, Diesel to HFO and vice versa on reduced load while synchronized. 
8. Unit 1 and 2 delivered ExWorks on 25 February and 15 March 2013. These units are currently in storage.
Unit 3 Unit to be delivered to storage in April 2013.
 
Details of the Scope of Supply:
 
 
Unit 1 / 9E tri-fuel ability PRICE (€uro)
Gas Turbine
Generator 25,000,000
Auxiliary Module
Other Material Shipped Directly (MSD)
Embedded Parts
Piping
Cables
 
Unit 2 / 9E tri-fuel ability
Gas Turbine
Generator 25,000,000
Auxiliary Module
Other Material Shipped Directly (MSD)
Embedded Parts
Piping
Cables
 
Unit 3 / 9E tri-fuel ability
Gas Turbine
Generator 25,000,000
Auxiliary Module
Other Material Shipped Directly (MSD)
Embedded Parts
Piping
Cables
 
Additional Scope
a) Addition of armoured LV cables between GE equipment;
b) Addition of piping between GE equipment;
c) Addition of historian;
d) Removal of generator circuit breaker and associated IPB
(Insulated phase bus duct).
3) Additional - two additional washing skid 4,250,000
4) Additional:
• Three (3) HFO Fuel Self Cleaning Filter Skids
• Three (3) Stainless Steel washable filtration cartridge for LDO
filtration skids
• Additional capacity on the three (3) washing skids
5) Additional price for Model Based Control (MBC)
6) Automatic water wash (excluding installation)
 
TOTAL SELLING PRICE (in Euros) 87,175,000
Quotation code: Clark1020130521
 




Copyright©2006-2013 Leda Greenpoweer Beijing ICP Reg. No: 10010978
   Fax:0086-10-84161062  E-mail:
[email protected]
[email protected]