480 | BUDGETARY PROPOSAL
For the Supply of
1x 9E.03 50HZ
UNITS EQUIPMENT
1 INTRODUCTION
This budget proposal has been prepared for the Supply of 1 x Frame 9E.03 gas turbine rated @ 132MW each
50Hz at ISO conditions.
Proposal Documents This proposal includes documents in the attached appendix, which are integral part of this
proposal:
? Appendix A: Fact Sheet 9E.03-.04
2 SCOPE OF SUPPLY
a. Gas Turbine Generator Equipment
Gas Turbine 9E.03 50HZ Gas Turbine Quantity 1
Combustion System Standard Combustor Fuel Heavy Fuel /
Liquid / Gas Diluent Water Injection
Auxiliary Equipment
Gas Turbine Package
? Gas Turbine enclosure
? Lubricating Oil and Hydraulic Oil Systems
? Lube Oil Piping and Reservoir
? Fuel Gas Module
? Liquid Fuel Module
Generator & Accessories
Air Inlet System
? Static - 3 Stage
Exhaust ? Diffuser
? Exhaust Silencer + Diverter Damper + Low Stack
Fuel System
? Distillate Fuel Heater
? Absolute Separator
? Liquid Fuel Filtering & Forwarding Skid
? Liquid Fuel Filtering Skid
Packaged Electronic and Electrical Control Cabinet (PEECC)
? Turbine Control Panel (TCP)
? Generator Control Panel (GCP)
? Motor Control Centre (MCC)
? Battery
? Battery chargers
? Human Machine Interface (HMI)
? Fire Fighting Protection Panel (FFP)
Other
? Washing Skid: Water Wash - 15hr Heating
? Fire Protection: CO2
? 1 LCI PER Unit
? GCB and Non Segregated Bus
? Unit Auxiliary Transformer
c. Customer Scope
We have listed for your convenience those major scope items which have not been included as the basis
of this Budgetary Proposal. Some of these items listed herein could be quoted separately as needed and
upon request.
This list is not exclusive and not limitative
? Civil Works
? Erection & Commissioning
? Site fire protection and detection system
? Off-base natural gas equipment (treatment station) if necessary
? Step-up transformer
? Cooling System
3 PERFORMANCE
The estimated performance rating for these units at ISO conditions are:
SC Net Output (MW) 132 SC Net Efficiency (%, LHV) 34.6%
SC Net Heat Rate (kJ/kWh, LHV) 10,403
The Estimated Plant level Performance at the flowing
parameters Temperature 320C Relative Humidity 85% NOx at
base load 75ppm at 15% O2 for HFO Noise 85 db Test
Tolerance +/- 1.5%
4 WARRANTY
GE standard warranty will be pass through to the buyer: Standard warranty terms are twelve (12) months starting from
the date fuel is first combusted in the Unit at the Site or eighteen (18) months from the date of Seller’s Notice of RTS,
whichever period shall first expire (the “Warranty Period�?.
5 DELIVERY
The unit is in storage in Europe at the moment and has been stored as per OEM specifications and are
ready for immediate shipment.
| | Used Power Plant | GE-9E.03/.04 | used power plant, equipment, spare parts, prior to sales, or just as information, not accurate or not for specific plant only. | | | |
Pubdate: 2022/4/26 16:56:24 |
|
Click add item to inquiry basket Click Copy Shared Links | Inquiry Basket |
Pageviews: 1
|
|
Statement: Any reference to the OEM part number or other OEM information is for the purpose of identification only and does not imply that the part was manufactured by the Original Equipment Manufacturer.
All the brands and trademarks in the whole domain of the website belong to their own owners and does not mean that we are their authorized partner or dealer. All the information in this website is only for reference, we do not assure its accuracy.
This statement supersedes all other claims and statements on all pages, files, pics and information within this whole web domain.
|
|