Quotation - Power plant 100MW |
No. | system unit | Name | Specification |
| Qty | Amount |
1 | GENERATOR SET 发电机组 | MAN 10L3244 Gensets | 5400KW 11KV 50HZ |
| 7 |
|
MAN18V2832 Gensets | 4000KW 11KV 50HZ |
| 6 |
|
MAN 18V3240 Gensets | 8700KW QQKV 50HZ |
| 5 |
|
2 | 电气系统 Electric system | 集中操作系统Central Operating System | Including parallel machine device 含并�?/span> |
| 3 |
|
辅助设备控制�?span style="">Auxiliary Equipment Control Panel | AC400V 50Hz AC230V 50Hz |
| 9 |
|
主发电机�?span style=""> Main Genset panel | AC11kv V 50Hz |
| 18 |
|
高压进线�?br/> HV carbinet (in) | KYN28-24, 630A, 25KA 11KV 50HZ |
| 3 |
|
高压出线�?br/> HV carbinet (out) | KYN28-24, 630A, 25KA 11KV +PT |
| 3 |
|
110V/24V直流�?br/> 110V/24V DC panel |
|
| 3 |
|
站用变压�?br/> Transformer for power plant | 11/0.4kV 50HZ 500kva |
| 3 |
|
3 | 燃油/润滑油系�?span style=""> fuel/lub-oil system | 柴油卸油单元 Diesel download unit | 50m3/h |
| 4 |
|
柴油输油单元 Diesel delivery unit | 20m3/h |
| 4 |
|
重油供应单元HFO supply unit | 2500L/hr 1.0mpa |
| 12 |
|
重油分离单元HFO separation unit | 2500L/hr 1.0mpa |
| 12 |
|
废气锅炉exhaust gas boiler | 1400kg/hr 1.0mpa |
| 6 |
|
滑油分离�?br/> Oil treatment seperator unit |
|
| 18 |
|
4 | 冷却水系�?/td> | 水冷却散热器 water cooler radiator |
|
| 18 |
|
5 | 排气系统EXHAUST GAS SYSTEM | 消声�?膨胀节Silencer,Expansion Bellows |
|
| 18 |
|
6 | 空气系统Air system | 空压机和空气�?span style=""> Air compressor and air bottle | 37m3/h,30bar,1000L, 30kg/cm2, |
| 6 |
|
7 | SCR尾气处理单元 | 2台发电机组共用SCR Two generating sets share one SCR |
|
| 9 |
|
8 | System Piping & Fitting & Auxiliary material系统管路、管件和�?助材�?/td> |
| Buyer's responsibility |
|
| 买家负责 |
9 | Cable ,Bridge & Stand & Install auxiliary materials电缆,桥架、支架和�?装材�?/td> |
| Buyer's responsibility |
|
| 买家负责 |
10 | Total Amount( Usd) FOB shanghai | US$ |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Notes: |
|
|
|
|
|
|
| 1. All prices base on FOB shanghai . |
|
|
| 2.Quality guaranty: Provide full warranty within one year from the date of delivery or 2000 operating hours, whichever comes first. |
|
| 3.Date of delivery: 6-8months after receipt of advance payment. |
|
|
| 4. Payment: 50 percent advance payment, 50 percent before shipment. |
|
|
| 5. Valid date for the offer: |
|
|
| 6. The offer is for equioment inside the power plant only. All civil work and fuel tanks should be taken out by customer. |
|
| 7. Installation guide and test: |
|
|
|
|
| a.USD x salary per day for one engineer (total 2 persons) during installation supervision and test (about 3 months). |
|
| b.USD x salary per day for one engineer (total 2 persons) during training and running (about 3 month). |
|
| c.The costs for traveling between China and customer, lodging and food shall be borne by customer. |
|